Input brief
Design and construct a 5-star luxury hotel in Perth CBD. 280 rooms, rooftop pool, spa. AUD $145M. 30 months. Target Green Star 5 and NABERS 5.5.
Sample generation time on fast mode: typically 1–3 minutes (not 47s marketing claim).
Perth CBD Luxury Hotel
Executive Summary
30-month design-and-construct delivery of a landmark 5-star hotel in Perth CBD under AS 4902-2000, targeting Green Star 5 and NABERS 5.5.
- Deliver 280 keys with rooftop pool and spa on programme
- Achieve certification targets without rework
- Maintain CBD logistics and stakeholder access
Approach: Staged pre-construction, substructure, and superstructure envelope with parallel fit-out waves and integrated commissioning.
- Dewatering failure in Perth limestone
- DM airspace permit delay for tower cranes
- Italian marble lead time 20 weeks
Work Breakdown Structure
Pre-Construction
12 wk- Site establishment & logisticsSite · 4w
- Design development & approvalsDesign · 8w
Substructure
14 wk- Dewatering & pilingCivil · 8w
- Basement structureStructure · 6w
Structure & Envelope
40 wk- Tower structure to level 28Structure · 28w
- Façade & weatherproofingEnvelope · 16w
Risk Register
| Risk | Prob | Impact | Mitigation |
|---|---|---|---|
| Dewatering failure in Perth limestone | High | High | Pilot wells, contingency pumps, geotech peer review |
| DM airspace permit delay for cranes | Medium | High | Early DM engagement, alternate crane radius plan |
| Italian marble lead time 20 weeks | High | Medium | Long-lead procurement at DD, approved alternates |